# How to track orders, lead times and deliveries on a design project

By Arnaud Doucet. Published August 12, 2026.

## Summary

- Track every item on its own record, from order to installation, rather than tracking whole orders. Orders split, and items arrive at different times.
- A lead time usually starts when the supplier confirms the order, not when the client approves it, so work back from the install date to find an order-by date.
- Every supplier email changes something, whether a reference, a date, a payment or a tracking number. Copy it onto the item as the email arrives, not in a weekly catch-up.
- Review open orders once a week (overdue, arriving soon, no date yet, payments due) and tell the client about a delay as soon as you know.

Once a client approves a selection, the design work on that item is done and the tracking starts. A residential project can easily have a hundred or more items, each on its own lead time, each producing its own trail of emails. Without a system, the schedule says one thing and the inbox says another.

## What should I track for each item after it's approved?

Track the order, the money, the shipment and the dates for every item: who you ordered from and under what reference, what's been paid and what's due, where the piece is, and when it's expected and needed. Keep it on the item itself, so anyone in your studio can answer "where's the sofa?" without searching email.

| Group | Fields |
| --- | --- |
| **Order** | Supplier, your PO number, the supplier's order number, order date |
| **Timing** | Quoted lead time, expected ship date, expected delivery date, install date |
| **Money** | Supplier deposit due and paid, supplier balance due and paid, client deposit and balance |
| **Shipment** | Carrier, tracking number or link, delivery address or receiving warehouse |
| **Issues** | Backorders, damage, substitutions, anything the client needs to hear about |

Track items rather than orders. One purchase order can cover six items that ship in three batches. If you only track the order, you can't record that four items have arrived and two are waiting on fabric.

## How do I turn a lead time into a delivery date?

Start from the date the supplier confirms the order, add the quoted lead time at the long end of the range, then add transit and receiving time. Lead times are usually quoted as a range of weeks, and the clock rarely starts on the day the client approves.

Work backwards from installation to find the latest date you can order:

1. **Install date:** when the piece needs to be in place.
2. **Minus receiving and delivery:** the time to receive, inspect and deliver to site.
3. **Minus transit:** how long shipping takes from the supplier.
4. **Minus the lead time,** at the long end of the quoted range.
5. **Minus deposit and confirmation time:** how long it takes to get the order acknowledged and the deposit paid.

The result is your order-by date. Anything still waiting for client approval close to that date is a risk to the install. That's why long-lead and custom pieces should be approved first.

When the order acknowledgment arrives, replace your estimate with the supplier's stated ship or completion date. From then on, track against the supplier's date, not the one you planned with.

## What should I do with each supplier email?

Copy the change onto the item as soon as the email arrives and check it against what you ordered.

| Email | What to check | What to record |
| --- | --- | --- |
| **Order acknowledgment** | Every line: product, finish, fabric, size, quantity and price | The supplier's order number, the confirmed ship or completion date, any changes to price |
| **Deposit invoice** | That the amount matches your order | The deposit amount and due date. Production often waits for it. |
| **Balance or pro forma invoice** | That the amount and remaining items are right | The balance due date. It's often required before the order ships. |
| **Shipping notice** | Which items shipped, and whether any are missing | Ship date, carrier, tracking number, revised delivery date |
| **Backorder or delay notice** | Which items, and the new date | The revised date, and a note to tell the client |
| **Delivery or receiving report** | Damage, missing pieces, wrong finish | Delivery date, and any claim you need to raise |

Read the acknowledgment line by line, every time. It's your first chance to catch a wrong finish or quantity before the piece is made, and it's often the last chance to change it.

Damage needs to be reported quickly. Carriers and receivers often set short windows for reporting it, so know what yours are and inspect deliveries promptly.

## How do I make supplier emails easier to match to a project?

Put your own reference on every order: your PO number and a sidemark with the client or project name. Then record the supplier's order number on each item as soon as you have it. Those references are how you, your receiver and any software connect an email back to the right project and items.

Where possible:

- Quote your PO number in the order email or on the order form.
- Ask suppliers to include the sidemark on acknowledgments, invoices and packaging.
- Use the same project name everywhere, rather than a client surname in one place and a street name in another.

In Inside Outside, you can forward supplier emails to your studio's private address. It reads the email, works out the project and items from those references, and suggests updates such as a confirmed date, a tracking number or a deposit due date. Nothing changes until someone in your studio reviews and applies the suggestions. It reads the email text only, not PDF attachments. See [Forward supplier emails](https://docs.insideoutside.com/ordering/forward-emails/) and [What does Inside Outside pick up from a forwarded email?](https://docs.insideoutside.com/ordering/what-gets-extracted/)

## What should I do when an order arrives in parts?

Record each partial shipment against the items it contains, keep every tracking number, and only mark an item delivered when all of it has arrived. Partial shipments are normal, for example a dining table arriving before its chairs, or a sectional arriving in two deliveries.

The [Track project deliveries skill](/field-guide/track-project-deliveries) uses supplier notices and carrier updates to match each shipment to an item and flag what is still outstanding.

1. **Match the shipment to items,** using the packing list or shipping notice.
2. **Record the tracking number** on each item in that shipment, and keep earlier tracking numbers in the item's notes.
3. **Mark delivered only what's complete.** A three-piece sectional with two pieces delivered isn't delivered.
4. **Note what's still outstanding** and its expected date.
5. **Check quantities** against your order. A shipped quantity that doesn't match the order is worth a call to the supplier the same day.

## How often should I review open orders?

Once a week, look at four lists: deliveries that are overdue, deliveries due in the next week, items with no delivery date, and payments coming due. It catches problems while there's still time to act.

- **Overdue:** contact the supplier for a revised date.
- **Arriving next week:** confirm receiving or site access, and that someone will be there.
- **No date yet:** chase the acknowledgment.
- **Payments due:** pay supplier deposits on time, because production often waits for them, and invoice client deposits before you're out of pocket.

Inside Outside's Procurement view groups a schedule's items by the week they're expected, with counts for overdue deliveries, arrivals in the next seven days, delivered items and items with no date, plus a filter for overdue payments. See [Track procurement](https://docs.insideoutside.com/ordering/track-procurement/).

## When should I tell a client about a delay?

As soon as you know, with the new date and what it affects. Clients take a delay better in week six than in installation week, and an early warning gives you time to offer an alternative if the new date doesn't work.

A useful delay message says:

- **What's delayed,** and the supplier's reason if they gave one.
- **The new expected date,** and how confident the supplier is in it.
- **What it affects,** such as the install date or a room that can't be finished.
- **The options,** if there are any: wait, choose an in-stock alternative, or install in phases.

Record the delay on the item as well as telling the client, so the schedule and your messages say the same thing.

## What should I do before installation day?

A week or two before installation, confirm that every item for the install is delivered, inspected and accounted for, and that anything still missing has a date the client knows about. Then plan the install around what's actually there.

1. **List every item for the install** and its status.
2. **Confirm what's at the receiver or on site,** and that it's been inspected.
3. **Chase anything outstanding** for a firm date.
4. **Tell the client what won't be ready,** and whether it'll be a second visit.
5. **Settle outstanding supplier and client payments** that the delivery depends on.

## Frequently asked questions

### When does a lead time start?

Usually when the supplier confirms the order, and for many trade orders only once your deposit has been received. Check the order acknowledgment, which should state the expected ship or completion date.

### What is a sidemark?

A sidemark is the client or project name the supplier puts on your order, its paperwork and its packaging. It tells you, your receiver and the supplier which project a piece belongs to.

### Should I mark an item delivered when part of it arrives?

No. Record each partial delivery with its tracking details, but only mark the item delivered when everything for that line has arrived and been checked.

### How often should I chase suppliers?

Review open orders weekly and contact a supplier as soon as an expected date passes without news. A short check-in a few days after a missed ship date is easier than discovering the delay at installation.